US 395 - NSC - US 2 to Wandermere & US 2 Lowering

Quarterly Project Report Update for Quarter Ending June 2009

Project Title & Location
NSC-US 2 to Wandermere & US 2 Lowering - Construct New Roadway

Project Description
Constructs four new drivable lanes of the North Spokane Corridor between Farwell Road and Wandermere including a new connection to US 395 at Wandermere. Constructs an interchange at US 2. This project will increase capacity and reduce travel time. There will be four lanes when this project is completed.

Contractor/Consultant
US 2 Lowering - Awarded to Graham Construction Management, Inc. of Spokane; US 2 to Wandermere Project not yet advertised or awarded

Recent Progress
This project will have two contracts.  The PS& E for the first, US 2 Lowering, was advertised on August 18, 2008 with bid opening on October 16, 2008.   The Contractor has excavated over 320,000 CY of material, constructed 153 out of 162 H piles for retaining wall 2, and has installed 30% of the timber lagging.  Over 50% of the piling for the bridge footings have been driven.  Footings, columns and abutments are being constructed for the LL, LR and EW-N bridges over US 2.  Concrete girders are being cast by Central Pre-Mix.

The PS&E for the second project, US 2 to Wandermere advertised on May 26, 2009.

Design Construction Impacts
The Region continues to monitor the overall cost of the NSC projects and is continually investigating methods to build the project as scoped for the least possible dollars.

Environmental Impacts / Compliance
No impacts at this time.

Impacts to Traffic
The Stage 2 traffic control plan was implemented with two northbound lanes and one southbound lane on US 2.

Project Milestones Scheduled Attained Milestone Outlook
Start of Project April 2004 April 2004
Right of Way Spring 2008   July 2008 US 2 Lowering - We have completed 30 of 32 parcels.  Of the remaining 2 parcels 1 has signed P&U, 1 has agreed and awaiting paperwork. US 2 to Wandermere - No ROW
Environmental Permits Spring 2008  April 2009  Complete
Contract Advertisement August 2008  August 2008  The US 2 lowering contract advertised on Aug. 18, 2008. The US 2 to Wandermere advertised on May 26, 2009 to coordinate these two sections opening to traffic simultaneously.
Open to Traffic May 2011 The open to traffic date is being evaluated based on the contractor's progress.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 7.4 5.5
Right-of-Way 2.6 1.9
Construction 124.3 92.6
Funded Project Costs 134.3 100

Nickel funds included in above costs

105.4 78.5

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Larry Larson, WSDOT Project Engineer @ (509) 324-6089 or E-mail: LarsoLR@wsdot.wa.gov