US 395 - NSC - US 2 to Wandermere & US 2 Lowering

Quarterly Project Report Update for Quarter Ending December 2007

Project Title & Location
NSC-US 2 to Wandermere & US 2 Lowering - Construct New Roadway

Project Description
Constructs four new drivable lanes of the North Spokane Corridor between Farwell Road and Wandermere including a new connection to US 395 at Wandermere. Constructs an interchange at US 2. This project will increase capacity and reduce travel time. There will be four lanes when this project is completed.

Contractor/Consultant
Project not yet advertised or awarded

Recent Progress
This project will have two contracts.  The PS& E for the first, US 2 Lowering, is approximately 60% complete.  The PS&E for the second, US 2 to Wandermere is approximately 30% complete.  Work on this project has increased recently due to completion of the Francis Avenue to Farwell Road Project. Ongoing work in the Project Office includes hydraulic design, finalizing the US 2 interchange plans for approval, continuing staging plan design, designing frontage roads, traffic analysis and preparing preliminary contract plan sheets.

Design Construction Impacts
The Region continues to monitor the overall cost of the NSC projects and is continually investigating methods to build the project as scoped for the least possible dollars.

Environmental Impacts / Compliance
No impacts at this time.

Impacts to Traffic
No impacts at this time.

Project Milestones Scheduled Attained Milestone Outlook
Start of Project April 2004 April 2004
Right of Way Spring 2008    We have completed 21 of the 33 parcels (63%) for this project.  All appraisals completed, and are in negotiation. 1 of the 12 remaining is in condemnation. 
Environmental Permits Spring 2008   NEPA Complete. Target SEPA comp=1/4/08. Target Sec. 106 update complete=1/31/08. Target permits complete=8/4/08. Permits needed=USACE 404, DOE 401, WDFW HPA, Spokane County Floodplain & Shoreline (CAO) Permits.
Contract Advertisement August 2008    The US 2 lowering contract will advertise in Aug. 2008, the US 2 to Wandermere contract will advertise by Aug 2009 to coordinate sections opening to traffic simultaneously.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 7.4 5.7
Right-of-Way 2.6 2.0
Construction 120.5 92.3
Funded Project Costs 130.5 100

Nickel funds included in above costs

100.9 77.3

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Larry Larson, WSDOT Project Engineer @ (509) 324-6089 or E-mail: LarsoLR@wsdot.wa.gov