WSDOT Projects

text size: T T T

US 395/North Spokane Corridor/Construction Photos

Groundbreaking Ceremony
North Spokane Corridor Groundbreaking ceremony on August 22, 2001.

WSDOT Maintenance Grading on NSC
WSDOT Maintenance crews doing the first work on the North Spokane Corridor during the Spring of 2001.  The team did the preliminary earthwork needed for utility line relocation prior to the first contract.

NSC Grading
Work on the first major contract on the North Spokane Corridor-Hawthorne Road to US 2 on March 19, 2002.  This was a grading job near the Kasier/Mead plant. 

More grading
More grading work on the first contract in March, 2002.

A look from the air
The NSC/Parksmith Road Interchange on March 29, 2002.

Another aerial
A close-up aerial of the Parksmith Road interchange taking shape in late March, 2002.

April 2002 aerial
The freeway starts to take shape.  Looking south from Farwell Road on April 19, 2002.

Farwell bridge girders
The next project:  Farwell Road Lowering and bridges.  The first girders going up on February 9, 2004.  The girders are over 130 feet long.

More bridge girders
Trucks lined up with more girders to be placed.

Waiting for Spring!
Bridge girders in place over Farwell Road on December 27, 2004.  Waiting for Spring to finish the job.

Pouring the deck
Pouring the concrete deck on one of the NSC bridges over Farwell Road on April 6, 2005.

More concrete!
More concrete going into the bridge deck on April 6, 2005.

The Farwell road bridges from the air
An aerial view of the completed Farwell Road bridge decks on May 25, 2005.

Clearing the way for the NSC
The next project:  Gerlach to Wandermere Grading.  The contractor is clearing the right of way on May 22, 2005 in preparation for earthwork.

More clearing
More clearing work.  Looking east from existing US 395 near Wandermere Golf Course.

Aerial view of grading
Right of way cleared and ready for earthwork.  Looking west toward the existing US 395 at Wandermere on May 25, 2005.

US 2 detour and Farwell Bridges
The US 2 detour being prepared for a temporary bridge over the earthwork haul route.  The new Farwell Road bridges and Farwell detour are just to the right of the new detour.  Photo taken May 25, 2005.

Looking north from Gerlach
Looking to the north from the Gerlach Road vicinity on May 25, 2005.  The material from the section between US 2 and Wandermere will be hauled to this area.

Market St. Detour Aerial
Aerial photo of Market Street detour on July 15, 2005.  Looking east.  Hawthorne Road is at the bottom of the photo.

Wandermere Earthwork Aerial
Aerial photo of earthwork near the Wandermere Golf Course on July 15, 2005.  Looking to the east.  Northwood Middle School is at the top of the photo with the Wandermere Pond at the bottom.

NSC Earthwork Aerial Photo
A close up of the earthwork on 7-15-05.

US 2 Haul Road Bridge Construction
Continued work on the US 2 haul route on July 15, 2005.  When complete, the highway traffic will cross over on a temporary bridge at this location.  This will allow trucks filled with dirt to pass under the highway and not tie up US 2 traffic.  The photo is looking to the northeast.  Existing US 2 is at the bottom left of the photo.

NSC Aerial 8-24-05
Aerial view of the northwest end of the project on August 24, 2005.  Looking to the northeast.  Wandermere golf course is at the top of the photo.  Existing US 395 is at the bottom left.  In a future project, bridges will be built to connect the new freeway to the current highway.

NSC Aerial 8-24-05
Another view of the west end of the North Spokane Freeway on August 24, 2005.  This is looking to the south/southeast with the golf course in the foregoround.

NSC Aerial 8-24-05
A temporary construction detour for US 2 traffic near Shady Slope Road.  Existing US 2 and its intersection with Shady Slope Road is in the center foreground of the photo.  The detour is the darker pavement with the short bridge.  Construction traffic will cross under the highway traffic reducing impacts to motorists.  Photo taken on August 24, 2005.

Grading on North Spokane Freeway
Grading work on the North Spokane Corridor in January 2006.

June Construction near Wandermere
Graded freeway route near the Wandermere Golf Course in June 2006.  Looking to the northwest.  The rock face on US 395 near the Little Spokane river Bridge is in the background.



Graded freeway section in north Spokane near Perry Street in June 2006.  Looking southeast.


June 2006 aerial photo of the NSC north end.  The fill section for Perry Street will be replaced by a bridge.  The bridge work will be underway in 2007.


June 2006 aerial of new freeway alignment near Market Street.  Looking northeast.

Market girder
Setting girders on the new NSC Market Street bridge on February 28, 2007.


Market Girders
The next day (March 1, 2007) after the first girders are set.

Market street Bridge Aerial
Market Street Bridge under construction in October 2007.

Parksmith Road Bridge Aerial
Parksmith Road bridge under construction in October 2007.

Perry Road Bridge
Perry Road Bridge in October 2007.

US 2 Interchange
Two bridges for Shady Slope Road at the NSC/US 2 Interchange area under construction in October 2007.