US 395 - NSC - Francis Avenue to Farwell Road

Quarterly Project Report Update for Quarter Ending September 2005

Project Title & Location
NSC - Francis Avenue to Farwell Road - Construct New Roadway

Project Description
Constructs two lanes of the North Spokane Corridor between Farwell Road and Francis Avenue. Provides a new road between these two major county roads and completes the grading between US 2 and Wandermere. This project will increase capacity and reduce travel time. There will be two lanes when this project is completed.

Contractor/Consultant
Max J. Kuney Company and KLB Construction

Recent Progress

The project consists of four contracts.  The first contract, Farwell Road Lowering, has been completed and was opened to traffic on June 4, 2005.  The contract was completed under estimated costs.  The second contract, Gerlach to Wandermere Grading, has completed roadway clearing work with roadway excavation and embankment 40% complete.  The U.S. 2 detour was opened to traffic on September 2nd, 2005 and the Market Street haul road crossing was also completed.  The design of the third contract, Francis Avenue to U.S. 2 – Structures, is near 100% completion and is on schedule for advertisement at the end of 2005.  One final change to the project was the permanent elimination of the Parksmith rail spur realignment.  The spur realignment was originally intended to save structure cost and provide for a future Market Street and Stoneman Road intersection as part of the Spokane County Bypass plans.  A change in girder type reduced structure costs and the change in the county bypass plans eliminated the need to rebuild the intersection at Market and Stoneman.  Redesign of structures and elimination of the spur realignment reduced costs approximately $1million.  The PS&E for the fourth contract, Francis Avenue to U.S. 2 – Grading and Paving, is approximately 30% complete and on track to meet the October 2006 ad date.  The 90% complete bridge plans for Lincoln Road, Gerlach Road, and the Pedestrian/Bicycle crossing at Parksmith will be completed in late September 2005.  To save costs for hauling materials a new quarry near the new roadway is being developed with the project.  A rezone application for the proposed Blystone Quarry was submitted to Spokane County on August 17, 2005.  A hearing date has not yet been set for this application.  The design team is progressing with remaining plans, specifications, and estimate along with the Hydraulic design.

 

 

Design Construction Impacts

As noted in the March 2005 and June 2005 Gray Notebooks, costs for both Nickel funded projects on the North Spokane Corridor could increase at completion in 2011, due to higher than anticipated costs in Right of Way acquisition and construction materials.  The region is investigating project design changes to reduce costs and develop alternative funding proposals to address this cost increase

Environmental Impacts / Compliance
No impacts at this time

Impacts to Traffic
The US 2 detour is open to traffic, no restrictions are anticipated.  Market street is reopened to traffic, with the haul road structure in use no traffic impacts are expected.  Napa Road was closed and cul-de-sacs were built at Winger Road and Garden Road. 

Project Milestones Scheduled Attained Milestone Outlook
Start of Project July 2003 July 2003
Right of Way August 2003 January 2004 Right-of-way acquisition delays were experienced due to the statutory imposed condemnation and relocation process involving two different privately owned properties.
Contract Advertised September  2003 January 2004 A delay in completing the Right of Way Acquisition resulted in the delay for the advertisement of the first contract Farwell Road Lowering.
Open to Traffic March 2009 No impacts at this time.
 
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 5.8 5.4
Right-of-Way 41.0 37.8
Construction 61.5 56.8
Funded Project Costs 108.3 100

Nickel funds included in above costs

108.3 100

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Mike Gribner, WSDOT Project Engineer @ (509) 324-6095 or E-mail: GribnM@wsdot.wa.gov