US 395 - Columbia Drive to SR 240 Rebuild Interchange

Quarterly Project Report Update for Quarter Ending September 2006

Project Title & Location
US 395 - Columbia Drive to SR 240 Interchange Improvements

Project Description
This project will reconfigure the US 395/SR 240 Interchange south of the "Blue Bridge" in Kennewick, to improve traffic flow and reduce the risk of collisions.

Contractor/Consultant
N/A

Recent Progress
Design is progressing on the project based on the ultimate recommendation from the VE study done in April 2006. Initial design work indicates the cost to construct this improvement may be higher than budgeted.  Design survey has been completed.  Updated ortho photos have been taken for use in design. 

Design Construction Impacts
None

Environmental Impacts / Compliance
None

Impacts to Traffic
None

Project Milestones Scheduled Attained Milestone Outlook
PE Phase Start November 05 January 06 The two month delay should not affect the October 2008 Ad date.
Environmental Document Complete January 08 No impacts anticipated at this time.
Right of Way Certified August 08 No impacts anticipated at this time.
Contract Advertisement Date October 08 No impacts anticipated at this time.
Operationally Complete June 2011 No impacts anticipated at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $  3.0 15.8 %
Right-of-Way $  2.0 10.5 %
Construction $ 14.0 73.7 %
Funded Project Costs $ 19.0 100 %

Nickel funds included in above costs

2005 Transportation Partnership Account

$ 19.0 100 %

  For more information, go to www.wsdot.wa.gov/projects

Moe Davari, WSDOT Project Engineer

(509) 222-2402 or davarim@wsdot.wa.gov