US 395 - Columbia Drive to SR 240 Rebuild Interchange - Complete October 2009

Quarterly Project Report Update for Quarter Ending March 2006

Project Title & Location
US 395 - Columbia Drive to SR 240 Interchange Improvements

Project Description
This project will reconfigure the US 395/SR 240 Interchange south of the "Blue Bridge" in Kennewick, to improve traffic flow and reduce the risk of collisions.

Contractor/Consultant

Recent Progress
Preliminary engineering work has started.  Survey crews have been collecting topographic site data.

Design Construction Impacts

Environmental Impacts / Compliance

Impacts to Traffic

Project Milestones Scheduled Attained Milestone Outlook
PE Phase Start November 05 January 06 Two month delay not anticipated to affect contract advertisement date
Environmental Document Complete January 08
Right of Way Certified August 08
Contract Advertisement Date October 08
Operationally Complete June 2011
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $  3.0 15.8 %
Right-of-Way $  2.0 10.5 %
Construction $ 14.0 73.7 %
Funded Project Costs $ 19.0 100 %

Nickel funds included in above costs

2005 Transportation Partnership Account

$ 19.0 100 %

  For more information, go to www.wsdot.wa.gov/projects

Moe Davari, WSDOT Project Engineer  

(509) 222-2402 or davarim@wsdot.wa.gov