US 395 - Columbia Drive to SR 240 Rebuild Interchange

Quarterly Project Report Update for Quarter Ending December 2006

Project Title & Location
US 395 - Columbia Drive to SR 240 Rebuild Interchange

Project Description
This project will reconfigure the US 395/SR 240 Interchange south of the "Blue Bridge" in Kennewick, to improve traffic flow and reduce the risk of collisions.

Contractor/Consultant
N/A

Recent Progress

Regional Traffic Office has began analyzing the traffic data for this interchange.  We are continuing with the design based on the ultimate Recommendation 1 from the VE Team.   

Design Construction Impacts
None

Environmental Impacts / Compliance
None

Impacts to Traffic
None

Project Milestones Scheduled Attained Milestone Outlook
PE Phase Start November 05 January 06 The two month delay should not affect the October 2008 Ad date.
Environmental Document Complete January 08
Right of Way Certified August 08
Contract Advertisement Date October 08
Operationally Complete June 2011
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $  3.0 15.8 %
Right-of-Way $  2.0 10.5 %
Construction $ 14.0 73.7 %
Funded Project Costs $ 19.0 100 %

Nickel funds included in above costs

2005 Transportation Partnership Account

$ 19.0 100 %

  For more information, go to www.wsdot.wa.gov/projects

Moe Davari, WSDOT Project Engineer

(509) 222-2402  or  davarim@wsdot.wa.gov

  

Project Cost Summary reflects the March 2006 Approved Legislative Supplemental Budget