US 2 - Westwood Road to Pend Oreille County Line

Status

July 2014

  • Weekly Construction Update
  • Awarded to Spokane Rock Products with a construction bid of $1,600,000.
  • Construction underway as of July 7, 2014.  Work hours are 7 p.m. until around 6 a.m.

US 2 will be resurfaced with hot mix asphalt.

Why is WSDOT resurfacing this highway?
This project preserves the roadway by milling (grinding down) and repaving US 2.

The End Result
Upgrades the structural integrity and extends the life of the roadway.

Project Benefits
Paving upgrades the structural integrity and extends the roadway life.

What is the project timeline?
Work on the project should start and be completed in the 2014 construction season.

Financial Information

Financial Data for PIN 600230G
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $2,319
Total $2,319

Project signage will reflect the cost of construction engineering, project bid award and sales tax.

How can I get more information?
Contact:
Bob Hilmes, Project Engineer
2714 N. Mayfair
Spokane, WA 99207
509-324-6232