Project Title & Location
US 2/Wenatchee River Bridge-Replace Bridge
West of Leavenworth, MP 90.57 to MP 90.62
|
Project Description
This project will replace the existing narrow bridge with a new structure that meets current standards.
|
|
Contractor/Consultant
Project not yet advertised or awarded
|
|
Recent Progress
VE Study was completed April 9, 2009. The Plant Survey was completed May 14, 2009. The Cultural Resource Report was completed May 19, 2009.
|
|
Design Construction Impacts
Minor impacts to USFS campground and Hatchery Creek Rd. Construction will require staged bridge construction.
|
|
Environmental Impacts / Compliance
Known wetland impacts with mitigation off-site. Section 106 Consultation required with mitigation. Construction will require HPA and fish-windows for in-water work.
|
Impacts to Traffic
Short-duration closures of US 2 may be required. Two-way traffic maintained majority of construction.
|