WSDOT Projects

text size: T T T

US 2 - One Mile East of Index - Temporary Repair Photos - February 2007

Photo Gallery:
Damage Photos
January 2007
April 2007
June 2007
July 2007

February 1, 2007

Crews finish the first row of nails

This week, crews finished drilling the first row of nails into the hillside, and have begun on the second row.


The 2 inch drill bit used to drill the metal rods into the ground

The nails are led into the ground by this two inch sacrificial (meaning it stays in the ground) bit. Crews have drilled through a number of different types of earth including clay, wood, rocks and sand.

Crews install a drainage pipe upslope from the nailing

Crews are also installing a temproary drainage pipe on the north side of US 2. This pipe will divert water from the existing pipe under the roadway while crews make permanent repairs to it.

February 14, 2007

Inside the corroded pipe

The bottom of this existing pipe has corroded allowing water to seep into the hillside and saturate the earth. We are working this week to line the existing pipe with a new pipe.

Crews have finished installing 91 soil nails. This is up from the original 66 nails because crews ran into more unstable soil than they had expected. They have also installed the drainage mat and begun work on the concrete wall.

February 23, 2007

Crews work to connect the sections of pipe

This week crews connected five 25-foot pipes that will line the corroded pipe. To connect them, crews used a type of welding technique that heats the ends of the pipe then pushes them together. Once they cool they are permanently bonded.

The 125 foot pipe being picked up and moved

Crews maneuver the pipe through the woods

Once crews had a complete 125-foot-long pipe, they had to pick it up and maneuver it through the woods to align it with the current pipe.

Crews push the new pipe inside the old pipe

Then they threaded the new pipe into the old, corroded pipe to give it a new lining.

The concrete wall is now complete

Crews have also completed the concrete portion of the soil nail wall.