View entire map. This US 2 paving project, from Milepost 100 to MP 110, is located in central Chelan County.
View entire photo. A right turn lane for westbound traffic was constructed at the Deadman Hill/Saunders Rd. intersection at MP 105.

View entire photo One lane of traffic in each direction was maintained throughout the paving process.
Overview
This preservation project paved 8.5 miles of US 2/97 from Leavenworth to Cashmere.
 | Improves Safety
This project provides a smoother driving surface. Includes a new right turn lane for westbound traffic at Deadman Hill/Saunders Rd. and other safety improvements including new signs, delineators, recessed pavement markers and striping.
|
 | Economic Incentive
The repaving project prevents further deterioration to the existing roadway at the least possible "life cycle" cost.
|
Partnerships & Cooperation
Central Washington Asphalt, inc. was the contractor on this project.
Funding
This project was funded through the following sources:
- Pre-existing gas tax - $3.9 million
- Total funding from all sources - $3.9 million
Contact Us
Mike Fleming, Project Engineer
WSDOT North Central Region
P.O. Box 98
Wenatchee, WA 98807
Phone: (509) 667-2870 or toll free (888) 461-8816
Email:fleminm@wsdot.wa.gov