View entire map The orange line shows the nearly 10 mile section of US 2 from Leavenworth to the Tumwater Campground that was paved.
View entire photo This is how the new pavement looked in July, 2009. (After)

View entire photo US 2 through Tumwater Canyon was paved in this project. (Before)
Project Complete July 2009
Construction began June 1 and was complete July 23, 2009.
This preservation project paved 9.96 miles, which began at MP 89.14 (near the Tumwater Campground) and ended at the west city limit of the town of Leavenworth.
Why is WSDOT
paving US 2?
The project upgrades the structural integrity and extends the life of the existing pavement, improving the ride as well as providing drainage and safety improvements.
The End Result
The project preserves the roadway, improves safety and reduces maintenance costs.
Project Benefits
- Extends roadway life
- Provides a smoother driving surface
- Upgraded deficient safety items
What is the project timeline?
Construction began June 1 and was complete July 23, 2009.
Financial Information
This project was advertised for private contractor bids on March 16, 2009. Two qualified bids were opened on April 16th. On April 20th, contract #7716 was awarded to Central Washington Asphalt, Inc. for $1,683,781.53, 23% below the engineering estimate.
- Pre-existing gas tax - $2.68 million
- Total Funding from all sources - $2.68 million
How can I get more information?
Contact:
Kevin Waligorski Project Engineer
WSDOT North Central Region
2830 Euclid Ave
Wenatchee, WA 98807
Phone: (509) 667-2860 or toll free (888) 461-8816
E-mail: waligok@wsdot.wa.gov