US 2 - Eagle Falls Vic to Tye Creek - Resurfacing

Status

September 2017

  • Construction is underway with weekday lane closures from 7 a.m. to 7 p.m. and weeknight lane closures from 6:30 p.m. to 5:30 a.m. 
  • Drivers should expect up to 30 minute delays during the day due to shorter work zones. Drivers should anticipate nighttime delays of approximately 30 minutes.
  • Sign up for email updates about this project and other state roadwork in Snohomish County.

Overview
A major road rehabilitation project is underway on US 2 between Gold Bar and Skykomish. Contractor crews are resurfacing three segments totaling almost 17 miles of roadway. The project is a split between chip sealing and repaving. Two segments totaling more than eight miles will be chip sealed, while the other eight-mile segment will get a new layer of asphalt.

Why is WSDOT resurfacing 17 miles of US 2 between Gold Bar and Skykomish?
It has been almost 20 years since some of these sections of US 2 were last repaved, and the highway is showing its age. Cracks, ruts and potholes are littered throughout this stretch of highway. This could create conditions where water can pool and freeze, making it difficult to drive. About 6,600 vehicles use this corridor every day, and about 6 percent of the total is truck traffic.

The End Result
This project will improve driver safety, the ride quality of the highway and extend the life of the roadway. It will also reduce the potential for emergency closures and costly repairs.

Project Benefits
• Preserves infrastructure and extends the life of the highway.
• Reduces the need for costly emergency maintenance repairs and unexpected closures.

What is the project timeline?
April 2017: Advertised for competitive bidding.
May 2017: Central Washington Asphalt, Inc. selected as contractor.
July 2017: Construction scheduled to start.
Fall 2017: Construction is scheduled to be completed.

Financial Information

Financial Data for PIN 100251C, 100256A, 100261B
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $3,280
CWA $1,125
Total $4,404