|
Project Title & Location
US 2/Dryden-Signal - Dryden
|
Project Description
Install traffic signal system to reduce traffic conflicts and accidents.
|
|
Contractor/Consultant
Project not yet advertised or awarded
|
|
Recent Progress
A Project Control Form has been approved to advance the construction of this project to the summer of 2007 to coincide with a planned paving project, for cost savings and efficiency.
|
|
Design Construction Impacts
The Dryden community has been requesting this signal for a number of years. This project was also identified as part of a Corridor Study conducted on US 2/97 between Peshastin and Wenatchee in June of 2002. There have been several meetings in the past with the community concerning the signal. As part of this project an on connection ramp from a frontage road will be closed and Alice Ave., a nearby intersection, will be restricted to right turn only.
|
|
Environmental Impacts / Compliance
A draft Environmental Classification Summary was completed October 1997. Under NEPA guidelines, the project is categorized as a Documented CE (Categorical Exclusion) and Categorically Exempt under SEPA guidelines.
|
Impacts to Traffic
Occasional lane closures can be anticipated during construction. Also, modifications will occur to the existing paint striping.
|