US 2 - Dryden - Complete August 2007

Quarterly Project Report Update for Quarter Ending June 2004

Project Title & Location
US 2/Dryden-Signal - Dryden

Project Description
Install traffic signal system to reduce traffic conflicts and accidents.

Contractor/Consultant
Project not yet advertised or awarded

Recent Progress
In April 2002, 70% of the survey and data collection was completed.  Remaining fieldwork and design work will begin Fall 2004.  A Project Control Form has been submitted for approval to advance the construction of this project to the summer of 2007 to coincide with a planned paving project, for cost savings and efficiency.

Design Construction Impacts
The Dryden community has been requesting this signal for a number of years.  This project was also identified as part of a Corridor Study conducted on US 2/97 between Peshastin and Wenatchee in June of 2002. There have been several meetings in the past with the community concerning the signal.  Prior to this project an on connection ramp from a frontage road will be closed and Alice Ave., a nearby intersection, will be restricted or closed. 

Environmental Impacts / Compliance
A draft Environmental Classification Summary was completed October 1997.  Under NEPA guidelines, the project is categorized as a Documented CE (Categorical Exclusion) and Categorically Exempt under SEPA guidelines.

Impacts to Traffic
Occasional lane closures can be anticipated during construction.  Also, modifications will occur to the existing paint striping.                

Project Milestones Scheduled Attained Milestone Outlook
Contract Advertised August 2007 No issues at this time.
Contract Awarded October 2007 No issues at this time.
 Groundbreaking Spring 08 No issues at this time.
Open to Traffic Fall 08 No issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.06 m 18.8 %
Right-of-Way $0 0 %
Construction $0.26 m 81.3 %
Funded Project Costs $0.32 m 100 %

Nickel funds included in above costs

$0.26 m 81.3 %

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Joel Voth, WSDOT Project Engineer @ (509) 667-2870 or E-mail: VothJ@wsdot.wa.gov