Project Title & Location
US 2/Chiwaukum Creek-Replace Bridge
West of Leavenworth, MP 89.88 to MP 89.91
|
Project Description
This project will replace the existing narrow bridge with a new structure that meets current standards.
|
|
Recent Progress
Survey data acquisition completed August 22, 2006. Wetland survey complete August 10, 2006. Interdisciplinary Scoping Workshop with stakeholders from USFS, USACE, NOAA Fisheries and WSDOT completed August 29, 2006. Cultural resources survey initiated in August 2006. Geotechnical Exploration started September 2006.
|
|
Environmental Impacts / Compliance
Possible wetland impacts. Section 106 Consultation required. Construction will require HPA and fish-windows for in-water work.
|
Impacts to Traffic
Potential 1-lane with traffic signal and staged bridge construction.
|