US 2 - Chiwaukum Creek

Quarterly Project Report Update for Quarter Ending September 2006

Project Title & Location

US 2/Chiwaukum Creek-Replace Bridge

West of Leavenworth, MP 89.88 to MP 89.91

Project Description
This project will replace the existing narrow bridge with a new structure that meets current standards.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress

Survey data acquisition completed August 22, 2006.  Wetland survey complete August 10, 2006.  Interdisciplinary Scoping Workshop with stakeholders from USFS, USACE, NOAA Fisheries and WSDOT completed August 29, 2006.  Cultural resources survey initiated in August 2006.  Geotechnical Exploration started September 2006.

Design Construction Impacts

Construction will require staged bridge construction.

Environmental Impacts / Compliance

Possible wetland impacts.  Section 106 Consultation required.  Construction will require HPA and fish-windows for in-water work.

Impacts to Traffic

Potential 1-lane with traffic signal and staged bridge construction.

Project Milestones Scheduled Attained Milestone Outlook
Contract Advertised March 2011 No issues at this time.
Contract Awarded April 2011 No issues at this time.
Groundbreaking July 2011 No issues at this time.
Open to Traffic December 2012 No issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $1.395 19%
Right-of-Way $0.01 1%
Construction $5.995 80%
Funded Project Costs $7.40 100%

Nickel funds included in above costs

$0 0%

2005 Transportation Partnership Account

$7.40 100%

  For more information, go to www.wsdot.wa.gov/projects

Bob Romine, WSDOT Project Engineer @509-667-2880 or Email:  RomineB@wsdot.wa.gov