US 2 - Chiwaukum Creek

Quarterly Project Report Update for Quarter Ending June 2009

Project Title & Location

US 2/Chiwaukum Creek-Replace Bridge

West of Leavenworth, MP 89.88 to MP 89.91

Project Description
This project will replace the existing narrow bridge with a new structure that meets current standards.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress
VE Study completed April 9, 2009.  The plant survey was completed May 14, 2009.  The Cultural Resource Report was completed May 19, 2009.

Design Construction Impacts
Minor impacts to USFS campground, Chiwaukum Creek Road and Wenatchee River Road.

Environmental Impacts / Compliance
Known wetland impacts with mitigation on-site.  Section 106 Consultation required with mitigation.  Construction will require HPA and fish-windows for in-water work.

Impacts to Traffic
Two-way traffic maintained majority of construction with short duration flagger controlled traffic.

Project Milestones Scheduled Attained Milestone Outlook
Contract Advertised March 2011 No issues at this time.
Contract Awarded April 2011 No issues at this time.
Groundbreaking June 2011 No issues at this time.
Open to Traffic December 2012 No issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $1.395 19%
Right-of-Way $0.01 1%
Construction $5.995 80%
Funded Project Costs $7.40 100%

Nickel funds included in above costs

$0 0%

2005 Transportation Partnership Account

$7.40 100%

  For more information, go to www.wsdot.wa.gov/projects

Bob Romine, WSDOT Project Engineer @509-667-2880 or Email:  RomineB@wsdot.wa.gov