Project Title & Location
US 2/97 Peshastin East-Interchange - Peshastin

Project Description
Construct a new interchange at the junction of US 2 and US 97. This intersection is located 15 miles West of Wenatchee and 5 miles East of Leavenworth.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress

Right of Way property acquisition continues.  The Type A Hydraulic Report and Design Documentation Package have been completed and approved.  The design team has got the Plans and Estimate 60% complete.  They are working on staging plans and coordinating with the local transit company in regards to two bus stop.

 

 

Design Construction Impacts
Approximately 16 parcels will be impacted by this project.  There will be impacts to orchards and local businesses.  Utility relocations will include fiber optic, power, domestic water, and irrigation lines.  A park and ride lot and transit stop will be impacted with the location of the interchange and will therefore be reconstructed.   Purchasing Right of Way began in the Spring of 2006.

Environmental Impacts / Compliance

A Determination of Non-Significance (DNS) has been issued under the State Environmental Policy Act (SEPA).

Impacts to Traffic
Traffic will be impacted on US 97, US 2 and on local county roads.  On US 2, traffic will be detoured or shifted onto either side of the existing highway during construction.  On US 97, traffic will not be impacted until the major tie ins are made due to the proximity of the interchange to the existing US2/97 intersection.

Project Milestones Scheduled Attained Milestone Outlook
Contract Advertised September 07 Right of way acquisition began in the spring of 2006.
Contract Awarded October 07 No Issues at this time.
Groundbreaking Spring 08 No Issues at this time.
Open to Traffic Fall 09 No Issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $1.30 m 6%
Right-of-Way $6.80 m 31 %
Construction $13.48 m 58%
Funded Project Costs $21.6m 100%

Nickel funds included in above costs

$21.6 m 100%