US 2/97 - Peshastin East Interchange

Quarterly Project Report Update for Quarter Ending December 2007

Project Title & Location
US 2/97 Peshastin East-Interchange - Peshastin

Project Description
Construct a new interchange at the junction of US 2 and US 97. This intersection is located 15 miles West of Wenatchee and 5 miles East of Leavenworth.

Contractor/Consultant
KLB Construction, Inc.

Recent Progress

Orchard tree removal began October 1 along with utility relocation work and will continue through November of 2007.  Bids were opened November 15, 2007 with the low bid of $9.8 million being awarded to KLB Construction on November 19. 

 

 

Design Construction Impacts
There will be impacts to orchards and local businesses.  Utility relocations will include fiber optic, power, domestic water, and irrigation lines.  A park and ride lot and transit stop will be impacted with the location of the interchange.  These facilities will be reconstructed.

Environmental Impacts / Compliance
Environmental Documentation is complete.  No compliance issues.

Impacts to Traffic
Traffic will be impacted on US 97, US 2 and on local county roads.  On US 2, traffic will be detoured or shifted onto either side of the existing highway during construction.  On US 97, traffic will not be impacted until the major tie-ins are made due to the proximity of the interchange to the existing US2/97 intersection.

Project Milestones Scheduled Attained Milestone Outlook
Contract Advertised September 24, 2007 September 24, 2007 No issues at this time.
Contract Awarded October 22, 2007 November 19, 2007 No Issues at this time.
Groundbreaking March 17, 2008 No Issues at this time.
Open to Traffic October 30, 2009 No Issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $1.45 m 7%
Right-of-Way $6.8 m 32%
Construction $13.33 m 61%
Funded Project Costs $21.58 m 100 %

Nickel funds included in above costs

$21.58 m 100 %

2005 Transportation Partnership Account