US 2/97 - Peshastin East Interchange

Quarterly Project Report Update for Quarter Ending March 2004

Project Title & Location
US 2/97 Peshastin East-Interchange - Peshastin

Project Description
Construct a new interchange at the junction of US 2 and US 97. This intersection is located 15 miles West of Wenatchee and 5 miles East of Leavenworth.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress
WSDOT completed a Value Engineering (VE) Study for this interchange project on 8/22/03.  The VE team presented the region with a study report of their recommendations.  The recommendation was a diamond interchange at a significant decrease in cost.  The VE recommendation was accepted for a savings of $8.8 million to a total of $16.5 million.  The Design Team is currently working on the interchange layout and R/W impacts. A public open house was held on February 5, 2004.  An open meeting was conducted at Blue Bird Inc in Peshastin on February 13, 2004 at the request of Blue Bird management and local fruit growers.  Continuing coordination with property owners, legislative staff, and local agencies.

Design Construction Impacts
A Corridor Study was conducted on the stretch of US 2/97 from this intersection to Wenatchee with a final report issued June 20, 2002.  Open houses were conducted on April 21, 2001, November 7, 2001 and February 3, 2002 introducing the community and Chelan County to the proposed needs.  The community and local agencies will continue to be involved as the design progresses.  A park and ride lot and transit stop will be impacted with the location of the interchange and may therefore be relocated.  A design/access hearing is scheduled for the fall of 2004.  Purchasing Right of way will begin in the Summer of 2005.

Environmental Impacts / Compliance
Under NEPA guidelines, the project has been categorized as a Documented CE (Categorical Exclusion).  A Draft Environmental Classification Summary was completed in June 2003.

Impacts to Traffic
Traffic will be impacted on US 97, US 2 and on local county roads.  On US 2, traffic will be detoured or shifted onto either side of the existing highway during construction.  On US 97, traffic will not be impacted until the major tie ins are made due to the proximity of the interchange to the existing US2/97 intersection.  Final detour and staging plans will be completed in the  Spring of 2005.        

Project Milestones Scheduled Attained Milestone Outlook
Contract Advertised September 07 No Issues at this time.
Contract Awarded October 07 No Issues at this time.
Groundbreaking Spring 08 No Issues at this time.
Open to Traffic Fall 09 No Issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $1.30 m 7.8%
Right-of-Way $4.00 m 24.2 %
Construction $11.25 m 68.0 %
Funded Project Costs $16.55 m 100 %

Nickel funds included in above costs

$16.55 m 100 %

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Joel Voth, WSDOT Project Engineer @ (509) 667-2870 Or E-mail: VothJ@wsdot.wa.gov