Budget Information

US 12 - White Pass Washout


Project map thumbnail
Larger vicinity map
Map of the washout areas

Washout on US 12
Section of White Pass that washed out on Dec. 9, 2015.

Status

Spring 2016

  • Construction started May 9 to restore the damaged sections of White Pass.
  • Drivers could experience delays up to 15 minutes on each side of the pass weekdays only.
  • Drivers can check the weekly construction update for impacts and delays.

Why is WSDOT restoring US 12 over White Pass?
Washington State Department of Transportation maintenance crews and contractors Granite Construction, DBM and Stripe Rite worked around the clock for two weeks to reopen White Pass after a series of storm-related washouts and rockslides closed the highway Dec. 9, 2015. 

The End Result
Currently, there are two areas, one east and one west of the pass where traffic is reduced to a single lane.

Crews will return in spring 2016 to restore US 12 to full capacity.

Project Benefits
Repairs will increase the reliability of this highway and improve traffic flow.

What is the project timeline?
Spring 2016: Construction Begins
Summer 2016: Construction Complete

Financial Information

Financial Data for PIN 501216T, 501216U, 501216V
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $8,040
CWA $0
Total $8,040

Project signage will reflect the cost of construction engineering, project bid award and sales tax.

How can I get more information?
Contact:
Summer Derrey
WSDOT Communications
509-577-1943