Project Title & Location
US 12 - Tieton River East and West Bridges - Replacement
|
Project Description
This project will replace two structurally deficient bridges across the Tieton River with two wider bridges that meet current standards. A new, straighter roadway between the two bridges will be constructed, moving the roadway away from a rockfall hazard.
|
|
Contractor/Consultant
Project has not been advertised or awarded.
|
|
Recent Progress
WSDOT has made some adjustments to the profile of the original alignment to satisfy the Shorline and Critical Areas Ordinance (CAO) requirements for Yakima County. The JARPA has been submitted to Yakima County for approval.
|
|
Design Construction Impacts
The profile modifications to the alignment will possibly impact HQ Bridge from delivering a set of bridge plans for review in February 2009. This delay should not impact the current April 2009 advertisement date.
|
|
Environmental Impacts / Compliance
Yakima County has officially recommended that WSDOT design the project to use the existing road and reduce the new floodplain fills as much as possible. Under the county’s Shoreline Master Plan they need to be assured that the project is minimizing impacts to land area that is useable for shoreline.
|
Impacts to Traffic
We plan to utilize existing bridges to detour traffic.
|