US 12 - Tieton River East and West Bridges - Replacement

Quarterly Project Report Update for Quarter Ending September 2006

Project Title & Location
US 12 - Tieton River East and West Bridges - Replacement

Project Description
This project will replace two structurally deficient bridges across the Tieton River with two wider bridges that meet current standards. A new, straighter roadway between the two bridges will be constructed, moving the roadway away from a rockfall hazard.

Contractor/Consultant
Project has not been advertised or awarded.

Recent Progress

Design work continues on this project.  Conversations with impacted landowners (WDFW, USFS, BOR, the Nature Conservancy and a private party) have begun.  A formal meeting was held October 3, 2006 and will be followed by an agency meeting to discuss environmental issues in more detail.  The geotechnical report for the bridge construction is currently being drafted and the report for the earthwork has been completed.  An open house is scheduled for Fall 2006.

A combination Cost Risk Assessment /Value Engineering (CRAVE) was performed in August 2006.

Design Construction Impacts

The CRAVE identified several risks that, in addition to the escalation in construction costs, could push project costs beyond the approved budget.  At the 90% confidence level, the total project cost could be $13.1 million compared to the $10.6 million budgeted.

Environmental Impacts / Compliance
Minor wetland impacts anticipated.

Impacts to Traffic
We plan to utilize existing bridges to detour traffic.

Project Milestones Scheduled Attained Milestone Outlook
PE Phase Start April 01 April 01 Preliminary Engineering phase started.
Environmental Document Complete Oct 07 No impacts anticipated at this time.
Right of Way Certified Aug 08 No impacts anticipated at this time.
Contract Advertisement Date Sept 08 No impacts anticipated at this time.
Operationally Complete Oct 2010 No impacts anticipated at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $  2.6 24.5 %
Right-of-Way $  0.1  0.9 %
Construction $  7.9 74.6 %
Funded Project Costs $ 10.6 100 %

Nickel funds included in above costs

2005 Transportation Partnership Account

$ 10.0 94.3 %

  For more information, go to www.wsdot.wa.gov/projects

Graph includes $260K spent prior to January 2006
Troy Suing, WSDOT Project Engineer
(509) 577-1703 or suingt@wsdot.wa.gov