Design Construction Impacts
The CRAVE identified several risks that, in addition to the escalation in construction costs, could push project costs beyond the approved budget. At the 90% confidence level, the total project cost could be $13.1 million compared to the $10.6 million budgeted.
The Nature Conservancy is in the process of transfering property needed for the project to the Washington Department of Fish and Wildlife (WDFW). This transfer will require the WSDOT to facilitate a land exchange with WDFW instead of a typical property acquisition, taking more time than anticipated. No impacts to the Ad Date are anticipated at this time.
|