US 12 - SR 124 to McNary Pool - Complete November 2005

Quarterly Project Report Update for Quarter Ending June 2005

Project Title & Location

US 12/SR 124 to McNary Pool – Add Lanes –
Tri-Cities (Phase 2)     MP 295.2 to MP 299.3

Project Description
This project is the second phase of five phases that will reconstruct US 12 as a four lane divided highway from SR 124 to the Walla Walla River, and plan for the future four-laning from the Wallula Junction to Walla Walla.

Contractor/Consultant
 Steelman-Duff, Inc.  

Recent Progress

The Contractor began work on January 3, 2005.  On May 31, 2005, the two new US 12 eastbound lanes were opened to traffic.  Work continued through June toward completing construction of the new westbound acceleration / deceleration lanes, improving intersection radii, milling and paving the existing westbound US 12 lanes, and installing the permanent signals.    

WSDOT and the US Highway 12 Coalition hosted an Open House to celebrate progress on the US 12 corridor projects on May 11th in Burbank and May 12th in Walla Walla.

Design Construction Impacts

Construction has progressed well.  Potential project delays, due to signal pole materials procurement problems, have been avoided by use of a temporary signal at the US 12  / Humorist Road intersection.   

Paving operations are mostly complete.  Permanent signal and other miscellaneous work will continue through July.  All major work is expected to be completed by late July or early August.  Work will then likely be suspended until seeding operations can be completed in early October. 

We anticipate additional costs based upon quantity changes.  The primary reason is a substantial increase in crushed surfacing due to unanticipated loss of the rock in the sandy subgrade.  The predicted additional costs should be covered by the contingency funding.

Environmental Impacts / Compliance

An Environmental Assessment, a Section 106 study and a noise study were completed.  There were no adverse impacts created by this project. 

The US Army Corps of Engineers has confirmed that the "Talent Ruling" will not affect this project.  

 

A National Pollution Discharge Elimination System permit has been acquired for construction of this project.

 

Regional Construction staff, with support from Regional Environmental staff, continue to work with Contractor personnel to ensure compliance.

Impacts to Traffic

Impacts to the traveling public have increased due to work on the existing westbound lanes. 

WSDOT, WSP, and Steelman-Duff have worked with local businesses and schools, to minimize traffic impacts by adjusting work activities during peak hours.   One lane of traffic in each direction will be maintained at all times during construction. 

Five accidents, including a fatality, have occurred within the work zone.   WSDOT, the Contractor and the WSP continue to communicate and work together to minimize disruptions to the travelling public and to provide a work zone that is as safe as possible. 

Project Milestones Scheduled Attained Milestone Outlook
Start Project Jul 03 Jul 03
Environmental Document Jan 01 Jan 01 Environmental Assessment approved for corridor project. The EA has been updated.
Right-of-Way Clear Sept 04 Nov 04 Right of Way was cleared on November 30, 2004.
Contract Advertised Oct 04 Oct 04

Advertised on October 4, 2004.

Open to Traffic Oct 05 May 05 The two new eastbound lanes were open to traffic on May 31, 2005.  Periodic lane closures will be used as work continues.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $1.7 14.6 %
Right-of-Way $2.0 23.1 %
Construction $8.4 62.3 %
Funded Project Costs $12.1 100 %

Nickel funds included in above costs

$11.7 100 %

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Will Smith, WSDOT Project Engineer @ (509) 577-1844

Or E-mail: mailto:smithw@wsdot.wa.gov