Project Title & Location
US12/McNary Pool to Attalia - Add Lanes Tri-Cities (Phase 1)
|
Project Description
McNary Pool to Attalia is the first phase of five phases to reconstruct US 12 as a four lane divided highway from SR 124 to the Walla Walla River, and plan for the future four-laning from the Wallula Junction to Walla Walla.
|
|
Contractor/Consultant
Steelman-Duff, Inc - Clarkston
|
|
Recent Progress
The US 12 / McNary Pool to Attalia - Add Lanes project was completed on time in November of 2004. Scheduled completion date, November, 2004.
|
|
Design Construction Impacts
On April 20, 2004, the Washington State Department of Fish and Wildlife issued an amended Hydraulic Project Approval (HPA), advancing the in-water work period to June 15 from July 15, 2004. The amended HPA permit advanced the project completion date by one month.
|
|
Environmental Impacts / Compliance
The Federal Highway Administration performed a construction review on May 18, 2004, finding construction activities in compliance wth the HPA permit.
|
Impacts to Traffic
Construction activities during this quarter were located off the roadway.
|