US 12 - McNary Pool to Attalia - Complete August 2004

Quarterly Project Report Update for Quarter Ending December 2003

Project Title & Location

US12/McNary Pool to Attalia - Add Lanes
Tri-Cities (Phase 1)

Project Description
McNary Pool to Attalia is the first phase of five phases to reconstruct US 12 as a four lane divided highway from SR 124 to the Walla Walla River, and plan for the future four-laning from the Wallula Junction to Walla Walla.

Contractor/Consultant
Steelman-Duff, Inc - Clarkston

Recent Progress
Ther contractor requested and was grantedThe contractor requested and was granted a winter shutdown starting November 14, 2003.  Subgrade for the new roadway is completed.  Two asphalt base lifts were completed on the new eastbound alignment prior to the winter shutdown.  Final asphalt paving will be completed when construction resumes in spring 2004.  Asphalt paving is now approximately 50% complete.  Stage 1 bridge construction is 40% complete.  Contour grading of the Mitigation Area is complete, with topsoil and compost in place.  Planting to begin in March 2004.  The new boat launch facility, constructed as part of the mitigation, is complete and open to the public. 

Design Construction Impacts
The Construction office is working with the contractor and the regional Environmental office in an effort to advance the in-water work window from July 15 to June 1, 2004.  Removal of the old structure is the only in-water work for 2004.  If the advance is approved, Stage 2 bridge construction will start six weeks prior to the current project schedule, allowing for an earlier project opening for the public.

Environmental Impacts / Compliance
On 10/26/03, the project passed a federal and state environmental compliance review.  The nearby air quality monitoring station continues to record no problems, and the contractor ensures that dust is controlled at all times.   The cultural consultant was present on site as needed.

Impacts to Traffic
Impacts to traffic continue to be minimal.  The traffic revision on the bridge creating narrower lanes continued through this quarter; both lanes remained open at all times.  Delays caused by construction vehicles delivering surfacing materials and asphalt were frequent but brief in duration.

Project Milestones Scheduled Attained Milestone Outlook
Contract Advertised Apr 02 Oct 02 Funding was not available due to reductions in statewide allocation.  Region permitted to put project on AD with a controlled spending plan.
Contract Awarded Nov 02 Nov 02 Accomplished on schedule.
Groundbreaking Apr 03 Apr 03 Accomplished on schedule.
Open to Traffic Nov 04 New lanes should be available late spring 2004. Bridge to be completed Nov 2004.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $2.6 23.2%
Right-of-Way $0.6 4.9%
Construction $8.2 71.9%
Funded Project Costs $11.4 100.0%

Nickel funds included in above costs

N/A

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Moe Davari, WSDOT Project Engineer @ (509) 577-1872
or Email:  DavariM@wsdot.wa.gov