US 12 - Attalia Vicinity - Complete September 2007

Quarterly Project Report Update for Quarter Ending March 2008

Project Title & Location

US 12 - Attalia Vicinity - Add Lanes (Phase 3)
Tri-Cities

 

Project Description
Attalia Vicinity is the third phase of five phases that will reconstruct US 12 as a four lane divided highway from SR 124 to the Walla Walla River, and develop a plan for future four-laning from Wallula to Walla Walla.

Contractor/Consultant
Apollo, Inc. of Kennewick, Washington. 

Recent Progress
The project stayed on schedule and this new four lane section of US 12 was opened to traffic in early September. Seeding and fertilizing, and integrated vegetation management were completed in October. Project completion was celebrated with Senator Murray on October 18, 2007 with a ribbon cutting ceremony.

Design Construction Impacts
Generally, the project proceeded well and all impacts listed on the risk matrix were resolved.
Project work was completed in mid-October, after seeding and fertilizing and integrated vegetation management were completed. Project completion was well ahead of the initial December 2007 anticipated completion.
This project had several change orders and some items overran plan quantity. The railroads charged more money than was anticipated when the agreements were established. All changes combined are approximately 1% over the authorized amount set aside for the construction phase.

Environmental Impacts / Compliance
Regional Construction staff, with support from Regional Environmental staff, worked well with Contractor personnel to ensure compliance.

Impacts to Traffic
This four lane section of US 12 is now open to traffic.

Project Milestones Scheduled Attained Milestone Outlook
Start Project Jul 03 Feb 04 Start date delayed while waiting for approved project definition.
Environmental Document Jan 01 Jan 01 Environmental assessment was approved for the corridor project.   The EA has been updated with project specific details.
Right of Way Sep 05 May 06 The right of way acquisition has been completed.
Contract Advertised Oct 05 Dec 05 The contract was advertised on December 19, 2005.
Open to Traffic Dec 07 Sep 07 Opened to traffic 3 months ahead of schedule.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $  1.3  7.5%
Right-of-Way $  0.8  4.9%
Construction $ 14.9  87.6%
Funded Project Costs $ 17.0 100%

Nickel funds included in above costs

$ 15.0  88.2%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Will Smith, WSDOT Project Engineer
(509) 577-1844 or smithw@wsdot.wa.gov
Project Cost Summary and Scheduled Project Milestones reflect the April 2007 Approved Legislative Budget.