US 12 - Attalia Vicinity - Complete September 2007

Quarterly Project Report Update for Quarter Ending June 2007

Project Title & Location

US 12 - Attalia Vicinity - Add Lanes (Phase 3)
Tri-Cities

 

Project Description
Attalia Vicinity is the third phase of five phases that will reconstruct US 12 as a four lane divided highway from SR 124 to the Walla Walla River, and develop a plan for future four-laning from Wallula to Walla Walla.

Contractor/Consultant
Apollo, Inc. of Kennewick, Washington. 

Recent Progress
There are three major components on this project; earthwork, HMA paving, and constructing the new bridge. Earthwork is approximately 95% complete and HMA paving is 55% complete. Continued progress on both are dependent on completion of the new bridge.
The bridge deck pour is scheduled to begin June 19th and paving is scheduled to resume in July.
The ribbon cutting ceremony is scheduled for late August.

Design Construction Impacts
Generally the project has proceeded well. All impacts listed on the risk matrix have been resolved.
The contractor's current schedule shows substantial completion at the end of August 2007. Physical completion is anticipated mid-October, after seeding and fertilizing are complete. Project completion at that time would be well ahead of the initial December 2007 anticipated completion.
There have been several change orders to date and some items have overrun plan quantity. While more changes are anticipated through the remainder of the project, all changes combined are anticipated to be covered by the amount set aside for contract contingencies.

Environmental Impacts / Compliance
Regional Construction staff, with support from Regional Environmental staff, continues to work with Contractor personnel to ensure compliance.

Impacts to Traffic
Shoulder closures have been used primarily with lane closures used occasionally. The speed limit was reduced from 60 mph to 50 mph during the week days with lane closures. Traffic is now being delayed briefly; delays have not exceeded 15 minutes.

Project Milestones Scheduled Attained Milestone Outlook
Start Project Jul 03 Feb 04 Start date delayed while waiting for approved Project Definition.
Environmental Document Jan 01 Jan 01 Environmental Assessment was approved for the corridor project.   The EA has been updated with project specific details.
Right of Way Sep 05 May 2006 The right of way acquisition has been completed.
Contract Advertised Oct 05 Dec 05 The contract was advertised on December 19, 2005.
Open to Traffic Dec 07 The anticipated Open to Traffic date is end of Aug 07.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $  1.2   7.8%
Right-of-Way $ 1.0   6.5%
Construction $ 13.2   85.7%
Funded Project Costs $ 15.4 100%

Nickel funds included in above costs

$ 15.0  97.4%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

 Will Smith, WSDOT Project Engineer
(509) 577-1844 or smithw@wsdot.wa.gov

Project Cost Summary reflects the March 2006 Approved Legislative Supplemental Budget