US 12 - Attalia Vicinity - Complete September 2007

Quarterly Project Report Update for Quarter Ending June 2006

Project Title & Location

Attalia Vicinity – Add Lanes – Tri-Cities

(Phase 3)

MP 302.14 to MP 305.49

 

Project Description
Attalia Vicinity is the third phase of five phases that will reconstruct US 12 as a four lane divided highway from SR 124 to the Walla Walla River, and develop a plan for future four-laning from Wallula to Walla Walla.

Contractor/Consultant
Apollo, Inc. of Kennewick, Washington. 

Recent Progress
Agreements between Burlington Northern and Union Pacific railroads have been completed.  Bids were opened on May 24, 2006 and the project was awarded to Apollo, Inc. of Kennewick, WA.

Design Construction Impacts
Due to recent unpredictable escalation in asphalt costs, the contractor's bid came in at 8.9% over WSDOT's estimate.  The total projected cost to complete the project is estimated at $16.4 million compared to the $15.5 budgeted.

Environmental Impacts / Compliance
All necessary environmental permits have been issued. The additional environmental review to utilize the material source from Boise Cascade has been completed.  A Walla Walla County Conditional Use Permit has been approved.  

The US Army Corps of Engineers has confirmed that the "Talent Ruling" will not affect this project. 

Impacts to Traffic
We anticipate limited one-lane closures and brief delays to allow for the contractors'  truck operations during the construction phase.

Project Milestones Scheduled Attained Milestone Outlook
Start Project Jul 03 Feb 04 Start date delayed while waiting for approved Project Definition.
Environmental Document Jan 01 Jan 01 Environmental Assessment was approved for the corridor project.   The EA has been updated with project specific details.
Right of Way Sep 05 May 2006 The right of way acquisition has been completed.
Contract Advertised Oct 05 Dec 05

The contract was advertised on December 19, 2005.

Open to Traffic Dec 07 No impacts anticipated at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $  1.2   7.8%
Right-of-Way $ 1.0   6.5%
Construction $ 13.2   85.7%
Funded Project Costs $ 15.4 100%

Nickel funds included in above costs

$ 15.0  97.4%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Troy Suing, WSDOT Project Engineer @ (509) 577-1703

Or E-mail: mailto:suingt@wsdot.wa.gov