US 12 - Attalia Vicinity - Complete September 2007

Quarterly Project Report Update for Quarter Ending June 2004

Project Title & Location

Attalia Vicinity – Add Lanes – Tri-Cities

(Phase 3)

MP 302.14 to MP 305.49

 

Project Description
Attalia Vicinity is the third phase of five phases that will reconstruct US 12 as a four lane divided highway from SR 124 to the Walla Walla River, and develop a plan for future four-laning from Wallula to Walla Walla.

Contractor/Consultant
 Project not yet advertised or awarded. 

Recent Progress
Early design work continues on the project.  Preliminary design of the railroad bridge is planned to begin in July.  The Project Office has continued discussions with Boise Cascade on their access issues and are nearing an agreement.  We are working towards publishing the Findings and Order from the Access Hearing in the summer of 2004.  The Project Definition is awaiting headquarter's approval. 

Design Construction Impacts
Currently there are no impacts anticipated that could affect delivery dates.

Environmental Impacts / Compliance

There are no environmental impacts anticipated that would affect the delivery date.  The Environmental Assessment is being updated to evaluate project specific areas not covered in the original report.
We are awaiting a ruling from the US Army Corps of Engineers on impacts of the "Talent Ruling."  This ruling could potentially change the jurisdiction of certain ditches or canals that form a connection between a navigable water of the US and another waterbody.   Additional permitting may be required.

Impacts to Traffic

We anticipate limited one-lane closures and brief delays to allow for the contractors'  truck operations during the construction phase.

Project Milestones Scheduled Attained Milestone Outlook
Start Project Jul 03 Feb 04 Start date delayed while waiting for approved Project Definition.
Environmental Document Jan 01 Jan 01 Environmental Assessment approved for the corridor project.  We are currently updating the EA with project specific details.
Right of Way Sep 05 No impacts anticipated at this time.
Contract Advertised Oct 05 No impacts anticipated at this time.
Open to Traffic Dec 07 No impacts anticipated at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.7 6.8%
Right-of-Way $1.0 10.0%
Construction $8.6 83.2%
Funded Project Costs $10.3 100%

Nickel funds included in above costs

$10.3 100%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Troy Suing, WSDOT Project Engineer @ (509) 577-1703