Skip Top Navigation

US 12 – Nine Mile Hill to Woodward Canyon Vic (Ph. 7A) - Add Lanes

Status

March / April 2014

Phase 7A (9 Mile Hill to Woodward Canyon)                                      
WSDOT has complete about 30% of the design.

Why is WSDOT widening US 12?        
This project is part of a corridor plan to widen US Highway 12 from the junction of the Snake River and SR 124 to Walla Walla. Since 1991, this corridor has experienced over 1,079 collisions causing 414 injuries; including 30 deaths. To date, all but 24 miles have been replaced or widened to four lanes.

Each year over eleven million tons of cargo travel this section of US 12. Trucks and slow moving recreation vehicles create congestion on this two-lane section of the highway.

The End Result
Phase 7 of the corridor project widens US 12 from Nine Mile Hill to the Frenchtown Monument. This section of US highway 12 will be relocated up to one mile north and constructed as a four-lane divided highway. When construction funding becomes available, WSDOT and a contractor will construct approximately eleven miles of new highway with fewer curves and four intersections at Nine Mile Hill, Touchet North Road, Woodward Canyon Road and Lower Dry Creek Road.

Project Benefits

  • Increased safety. The proposed four-lane highway will increase safety by decreasing the number of intersections on US 12 while separating opposing traffic with a wide median. Roadway curves will be straightened and two new channelized intersections allow safe access to and from the new roadway.
  • Relieved congestion: A four-lane highway will improve traffic flow and provide for passing of longer, slower equipment.
  • Freight mobility: Building a four-lane highway will ease conflicts between slow moving trucks and passenger vehicles. Commercial trucks make up as much as 33 percent of the traffic stream, causing slowdowns and safety concerns.

What is the project timeline?
Limited funding is available to complete the design, begin contract plans, and to purchase a portion of the right of way needed for the project. 

Additional funding is needed to complete 30% of the design and purchase a quarter of the right of way needed. Once funding is available, it willl take about 18 months to complete the contract plans and begin construction.

Financial Information

Funding for the design and a portion of the right of way for this project comes from the following sources:

  • Federal Funding
    Existing Federal - $5.1 million
  • State Funding
    Existing Funds - $0.2 million
  • $2 million is available to begin purchasing right of way
  • Estimated total project cost (design, right of way, construction) - $132 million.  About $126 million is needed to complete Phase 7

Construction for this project is not yet funded


How can I get more information?
Contact:
Kerry Grant, WSDOT Design Project engineer
509-577-1760
Grantk@wsdot.wa.gov


Jason Smith, WSDOT Environmental Manager
509-577-1750
Smithjw@wsdot.wa.gov

back to top