US 12 - Naches River North of Yakima - Stabilize Slopes - Complete October 2008

Quarterly Project Report Update for Quarter Ending June 2008

Project Title & Location
US 12 - Naches River North of Yakima - Stabilize Slopes

Project Description
The area of US 12 along the Lower Naches River, near the 16th Avenue interchange, suffers from repetitive bank erosion and slope failures. Emergency work has been performed in this area four times since 1999. This project will correct this chronic environmental deficiency by moving the Naches River channel away from US 12, and construct a bio-engineered structure in the river to reduce future problems and protect the roadway and environment.

Contractor/Consultant
Scarsella Bros. Inc. of  Seattle Wa.

Recent Progress
Work started on June 16 at the beginning of inwater work window.

Design Construction Impacts

Environmental Impacts / Compliance
Field inspectors and region environmental staff will closely monitor construction and conduct water quality monitoring as needed

Impacts to Traffic
When work starts in June, US 12 westbound traffic will be restricted to one lane in the project area during work hours. Both westbound lanes will be open during non-work hours.

The project will also have a ramp closure / detour for traffic coming from Yakima on 16th Ave. going to westbound US 12. During ramp closures traffic will be detoured to North First St. in Yakima to get to westbound US 12.

Project Milestones Scheduled Attained Milestone Outlook
PE Phase Start Jan 04 Jan 04 On Schedule.
Environmental Document Complete Jan 07 Jan 07 On Schedule.
Right of Way Certification Sept 07 Oct 07 Completed in quarter, no impact to Operationally Complete date.
Contract Ad Date Oct 07 Nov 07 Delay due to Right of Way Certification will not impact Operationally Complete date.
Operationally Complete Dec 08 No impacts are anticipated at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $ 0.6 19.0 %
Right-of-Way $ 0.1  4.4 %
Construction $ 2.3 76.7 %
Funded Project Costs $ 3.0 100 %

Nickel funds included in above costs

2005 Transportation Partnership Account

$ 2.4 81.0 %

  For more information, go to www.wsdot.wa.gov/projects

Paul Gonseth, Project Engineer
(509) 577-1810 or gonsetp@wsdot.wa.gov

Project Cost Summary and Scheduled Project Milestones reflect the April 2008 Approved Legislative Budget.