US 12 - Frenchtown Vicinity to Walla Walla - Add Lanes

Quarterly Project Report Update for Quarter Ending September 2007

Project Title & Location
US 12 - Frenchtown Vicinity to Walla Walla - Add Lanes
Walla Walla County

Project Description
This project is phase six of eight phases that improve US 12 from SR 124 (Burbank) to Walla Walla. This approximately eight mile project will reconstruct US 12 from McDonald Road to Walla Walla as a four lane divided highway, with improved capacity and enhanced safety.

Contractor/Consultant
David Evans and Associates prepared the Resource Reports.  Landau and Associates have studied the springs near Pine Street. 

Recent Progress
The 90% complete plans were reviewed on August 7th.  The completed contract plans and specifications were turned in for review on August 21st. 

We have acquired 31 of 37 parcels, four are in negotiations, and two were submitted for condemnation and possession and use was granted. The four residential relocations are complete.

Design Construction Impacts
The project is on schedule, on budget, and on scope as per the approved 2007-2009 Transportation budget.

Environmental Impacts / Compliance
The Joint Aquatic Resource Permit Agreement (JARPA) and Conceptual Mitigation Plan were sent to all resource agencies on August 2nd. 

Impacts to Traffic
WSDOT will construct a 50 MPH detour at the Pine Street intersection for public safety. 

Project Milestones Scheduled Attained Milestone Outlook
PE Start April 05 July 05 Preliminary design work began under US 12 - Wallula to Walla Walla Planning Study.
Environmental Documentation May 06 Nov 06 NEPA and SEPA were complete in November 2006
Right of Way Certification Oct 07 No impacts anticipated.
Contract Advertisement Oct 07 No impacts anticipated.
Operationally Complete Jun 09 WSDOT anticipates the project will take two full construction seasons to complete. Approval to change the operationally complete date to Oct 09 will be requested as part of the 2008 Supplemental budget.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $  3.2 5%
Right-of-Way $  7.0 10%
Construction $56.2 85%
Funded Project Costs $ 66.4 100%

Nickel funds included in above costs

$1.4  2%

2005 Transportation Partnership Account

$51.3 77%

  For more information, go to www.wsdot.wa.gov/projects

Kerry J. Grant, WSDOT Project Engineer
(509) 577-1760 or grantk@wsdot.wa.gov