US 12 - Frenchtown Vicinity to Walla Walla - Add Lanes

Quarterly Project Report Update for Quarter Ending September 2006

Project Title & Location
US 12/McDonald Road to Walla Walla - Add Lanes
Walla Walla County

Project Description
This project is phase six of eight phases that improve US 12 from SR 124 (Burbank) to Walla Walla. This approximately eight mile project will reconstruct US 12 from McDonald Road to Walla Walla as a four lane divided highway, with improved capacity and enhanced safety.

Contractor/Consultant
David Evans and Associates prepared the Resource Reports.  Landau and Associates is studying the springs near Pine Street.

Recent Progress
The project office has completed a 30% design package for internal review.  Acquisition of right of way has begun.  Two parcels have already been acquired.

Design Construction Impacts
Recent cost escalations have increased the construction amount of this project by approximately 22%.  A majority of these increases can be attributed to rising fuel prices and asphalt oil used to make hot mix asphalt pavement.

Environmental Impacts / Compliance
The Environmental Assessment (EA) was published on May 15, 2006.  A Finding of No Significant Impact (FONSI) and State Determination of Non-Significance (DNS) will be issued by October of this year.

WSDOT is working with the Walla Walla County Watershed Planning group to find mitigation opportunities that benefit creeks, rivers, and fish habitat in Walla Walla County.

Impacts to Traffic
A majority of the project work will take place away from existing roadways. To keep traffic moving and increase safety at the Pine Street Intersection, WSDOT will construct a temporary detour which will allow traffic to continue to moving freely.

Project Milestones Scheduled Attained Milestone Outlook
Environmental Documentation May 06 The EA public comment period ended June 16.  The Documentation should be complete in October of 2006.
Design Documentation May 06 Design documentation is expected to follow the environmental documentation in October 2006.
Environmental Permits Oct 06 All environmental permits will be acquired by April 2007.
Right of Way Certification Oct 06

Right of way certification is scheduled for October 2007.

Contract Advertisement Nov 06 Contract Ad date is now scheduled for October 29, 2007.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $  3.1  6%
Right-of-Way $  7.0 14%
Construction $40.3 80%
Funded Project Costs $ 50.4 100%

Nickel funds included in above costs

$1.4  3%

2005 Transportation Partnership Account

$36.0 71%

  For more information, go to www.wsdot.wa.gov/projects

Kerry Grant, WSDOT Project Engineer
(509) 577-1760 or grantk@wsdot.wa.gov