|
Project Title & Location
US 12 - Frenchtown Vicinity to Walla Walla - Add Lanes Walla Walla County
|
Project Description
This project is phase six of eight phases that improve US 12 from SR 124 (Burbank) to Walla Walla. This approximately eight mile project will reconstruct US 12 from McDonald Road to Walla Walla as a four lane divided highway, with improved capacity and enhanced safety.
|
|
Contractor/Consultant
David Evans and Associates prepared the Resource Reports. Landau and Associates have studied the springs near Pine Street.
|
|
Recent Progress
The contract plans are complete. Project advertisement for bids was delayed until December 17, 2007 for acquisition of right of way. Bid opening is scheduled for January 30, 2008. Project construction should begin in the spring and is expected to take two years, ending in October 2009.
|
|
Design Construction Impacts
The project is on schedule, on budget, and on scope as per the approved 2007-2009 Transportation budget.
|
|
Environmental Impacts / Compliance
Environmental documentation and permitting is complete.
|
Impacts to Traffic
WSDOT will construct a 50 MPH detour at the Pine Street intersection for public safety.
|
| Project
Milestones |
Scheduled |
Attained |
Milestone Outlook |
|
PE Start
|
April 05
|
July 05
|
Preliminary design work began under US 12 - Wallula to Walla Walla Planning Study.
|
|
Environmental Documentation
|
May 06
|
Nov 06
|
NEPA and SEPA were complete in November 2006
|
|
Right of Way Certification
|
Oct 07
|
|
Ongoing negotiations delayed the Right of Way Certification until November 29, 2007.
|
|
Contract Advertisement
|
Oct 07
|
|
Advertisement date delayed until December 17, 2007 because of ongoing right of way negotiations.
|
|
Operationally Complete
|
Jun 09
|
|
WSDOT anticipates the project will take two full construction seasons to complete. Approval to change the operationally complete date to Oct 09 will be requested as part of the 2008 Supplemental budget.
|