US 12 - Clemons Road Vicinity

Quarterly Project Report Update for Quarter Ending September 2007

Project Title & Location

US 12 - Clemons Road Vicinity
Grays Harbor County

 

Project Description
This project will make safety improvements to US 12 between milepost 7.0 and 8.0, including the vicinity of the Clemons Road Intersection, and other high-risk areas along this corridor.

Contractor/Consultant
The project has not been advertised or awarded.

Recent Progress
The design concepts have been approved. The Intersection Plan for Approval has been reviewed by the Plans Office and is pending final review and approval.  The Real Estate Services Office has begun the Right of Way acquisition process. The contract plans, specifications, and estimates (PS&E) package is 60% complete. 

Design Construction Impacts
Some improvements being considered will require the relocation of buried and overhead utilities.

Environmental Impacts / Compliance
Some improvements being considered for this project will impact storm water runoff and roadside ditches.  Any necessary storm water treatment plans will be developed as part of this contract. 

Impacts to Traffic
During construction, the public can expect minor delays as traffic will be controlled by a combination of lane closures and flagging.

Project Milestones Scheduled Attained Milestone Outlook
Begin Preliminary Engineering Dec. 15, 2005 Nov. 23, 2005 Design concepts have been approved.
Environmental Documentation Complete June 1, 2007 Documentaion will be complete prior to advertisement.
Right of Way Certified Oct. 15, 2007 Needs have been identified and the acquisition process has begun.
Contract Advertisement Nov. 13, 2007
Operationally Complete July 31 ,2008
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.21 6.3%
Right-of-Way $0.23 7.0%
Construction $2.87 86.7%
Funded Project Costs $3.31 100.0%

Nickel funds included in above costs

2005 Transportation Partnership Account

$3.31 100.0%

  For more information, go to www.wsdot.wa.gov/projects

John Hart, project engineer, (360) 533-9352