Project Title & Location
US 12 - Clemons Road Vicinity Grays Harbor County
|
Project Description
This project will make safety improvements to US 12 between milepost 7.0 and 8.0, including the vicinity of the Clemons Road Intersection, and other high-risk areas along this corridor.
|
|
Contractor/Consultant
The project has not been advertised or awarded.
|
|
Recent Progress
The design concepts have been approved. The Intersection Plan for Approval has been reviewed by the Plans Office and is pending final review and approval. The Real Estate Services Office has begun the Right of Way acquisition process. The contract plans, specifications, and estimates (PS&E) package is 60% complete.
|
|
Design Construction Impacts
Some improvements being considered will require the relocation of buried and overhead utilities.
|
|
Environmental Impacts / Compliance
Some improvements being considered for this project will impact storm water runoff and roadside ditches. Any necessary storm water treatment plans will be developed as part of this contract.
|
Impacts to Traffic
During construction, the public can expect minor delays as traffic will be controlled by a combination of lane closures and flagging.
|