US 12 - Clemons Road Vicinity

Quarterly Project Report Update for Quarter Ending March 2007

Project Title & Location

US 12 - Clemons Road Vicinity
Grays Harbor County

 

Project Description
This project will make safety improvements to US 12 between milepost 7.0 and 8.0, including the vicinity of the Clemons Road Intersection, and other high-risk areas along this corridor.

Contractor/Consultant
The project has not been advertised or awarded.

Recent Progress
Preliminary concepts were developed to reduce the severity and rate of accidents, and to improve traffic movements, by enhancing the roadway and the channelization for this intersection. Recent changes in traffic patterns, accident rates and land use have forced us to reevaluate the improvements to the corridor. New traffic counts were conducted in the summer of 2006, and the analysis has been used to rescope this project.

Design Construction Impacts
Some improvements being considered may require the relocation of buried and overhead utilities.

Environmental Impacts / Compliance
Some improvements being considered for this project will impact storm water runoff and roadside ditches.  Any necessary storm water treatment plans will be developed as part of this contract. 

Impacts to Traffic
During construction, the public can expect minor delays as traffic will be controlled by a combination of lane closures and flagging.

Project Milestones Scheduled Attained Milestone Outlook
Begin Preliminary Engineering Nov. 22, 2005 Nov. 23, 2005 Project has been rescoped.
Environmental Documentation Complete Oct. 13, 2006 Delayed, and will affect overall project delivery.
Right of Way Acquisiton Oct. 13, 2006 Needs have been identified and the acquisition process can begin.
Advertisement Nov. 7, 2007
Estimated Open to Traffic Summer 2008
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.20 7.4%
Right-of-Way $0.22 8.1%
Construction $2.29 95.0%
Funded Project Costs $2.71 100.0%

Nickel funds included in above costs

2005 Transportation Partnership Account

$2.71 100.0%

  For more information, go to www.wsdot.wa.gov/projects

John Hart, project engineer, (360) 533-9352