Project Title & Location
US 12 - Yakima - 40th Avenue Interchange Improvements
|
Project Description
This project improves safety and traffic flow at the US 12/40th Avenue Interchange. Improvements include a second lane for the eastbound on-ramp, efficient signal phasing, and improved connections between the Yakima Greenway and local bike and pedestrian pathways. These upgrades will increase capacity, improve traffic mobility, and encourage commercial and industrial development in this area.
|
|
Environmental Impacts / Compliance
The project will be a SEPA - Determination of Non-Significance. The project will treat new stormwater runoff onsite as a result of new roadway constructed.
|
Impacts to Traffic
This project will require the eastbound off and the westbound on ramps to be closed one weekend to install a City of Yakima Sewer crossing. Reconstruction of the intersection will require a single lane closure. Construction of the westbound on ramp will require a lane closure on US 12 at times. Intersection closures will cause back-ups during high traffic flows.
|