Skip Top Navigation

Construction Photos

A shot of where the new ramp will connect to State Route 3.

Where the new on-ramp will instersect with SR 3.

The concrete bridge deck.

Construction of the bridge piers is complete. Last week crews poured concrete on the new deck.

Crews bring over 100 loads of fill material to the site each day.

Work crews bring in over 100 loads of fill material each day. The fill material is being used to build up the area around the bridge deck, so connections to SR 3 and US 101 will be level.


So far, over 16,000 tons of fill material has been brought to the site.

So far, over 16,000 tons of fill material has been brought to the work site. It is
estimated 25,000 tons will be used total.

Photo of pier drilling.
A giant auger is used to drill shafts for piers. After the shafts are drilled, reinforcing steel rebar cages are inserted in the shaft and concrete is poured.