|
Project Title & Location
US 101/SR 3 On Ramp to US 101 Northbound - New Ramp.
|
Project Description
This project will construct a new northbound on-ramp from SR 3 to US 101 which will provide an efficient and safe roadway for motorist. The existing at grade intersection currently requires northbound US 101 traffic to make a left turn against southbound US 101 vehicles.
|
|
Contractor/Consultant
Currently under WSDOT design.
|
|
Recent Progress
The project was awarded to Tri-State Construction on March 31, 2008.
|
|
Design Construction Impacts
All identified impacts have been addressed.
|
|
Environmental Impacts / Compliance
The permits for the project are complete.
|
Impacts to Traffic
There will be some flagger controlled night time lane closures during the construction of the northbound on-ramp. Bicycle traffic will be re-routed during the construction of the project.
|
| Project
Milestones |
Scheduled |
Attained |
Milestone Outlook |
|
Begin Preconstruction Engineering
|
May 15, 2005
|
Dec. 2005
|
Concept Approval on February 12, 2007. Project Management Plan endorsed on February 13, 2007.
|
|
Environmental Documentation Complete
|
May 5, 2008
|
Dec.2007
|
Documentation Complete.
|
|
Right of Way Certification
|
November 5, 2008
|
Nov. 2007
|
The current design will fit within existing right-of-way, no right-of-way phase needed.Right-of-way certification was obtained on November 14.
|
|
Project Advertisement
|
October 6, 2008
|
Feb. 2008
|
Completed, Advertised and Awarded.
|
|
Open to Traffic
|
December 31, 2009
|
|
With a February 2008 advertisement the project will be open to traffic in October 2008.
|