US 101 - SR 3 On-Ramp to US 101 Northbound

Quarterly Project Report Update for Quarter Ending March 2008

Project Title & Location
US 101/SR 3 On Ramp to US 101 Northbound - New Ramp.

Project Description
This project will construct a new northbound on-ramp from SR 3 to US 101 which will provide an efficient and safe roadway for motorist. The existing at grade intersection currently requires northbound US 101 traffic to make a left turn against southbound US 101 vehicles.

Contractor/Consultant
Currently under WSDOT design.

Recent Progress
The project was awarded to Tri-State Construction on March 31, 2008.

Design Construction Impacts
All identified impacts have been addressed.

Environmental Impacts / Compliance
The permits for the project are complete. 

Impacts to Traffic
There will be some flagger controlled night time lane closures during the construction of the northbound on-ramp.  Bicycle traffic will be re-routed during the construction of the project.

Project Milestones Scheduled Attained Milestone Outlook
Begin Preconstruction Engineering  May 15,  2005 Dec. 2005 Concept Approval on February 12, 2007. Project Management Plan endorsed on February 13, 2007.
Environmental Documentation Complete May 5, 2008 Dec.2007 Documentation Complete.
Right of Way Certification November 5, 2008 Nov. 2007 The current design will fit within existing right-of-way, no right-of-way phase needed.Right-of-way certification was obtained on November 14.
Project Advertisement October 6, 2008 Feb. 2008 Completed, Advertised and Awarded.
Open to Traffic December 31, 2009 With a February 2008 advertisement the project will be open to traffic in October 2008.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.55 14.2%
Right-of-Way $0.57 14.8%
Construction $2.76 71.0%
Funded Project Costs $3.89 100%

Nickel funds included in above costs

No 0%

2005 Transportation Partnership Account

 $3.89 100%

  For more information, go to www.wsdot.wa.gov/projects

John Ho, Project Engineer, (360) 570-6660.