Project Title & Location
US 101/SR 3 On Ramp to US 101 Northbound - New Ramp.
|
Project Description
This project will construct a new northbound on-ramp from SR 3 to US 101 which will provide an efficient and safe roadway for motorist. The existing at grade intersection currently requires northbound US 101 traffic to make a left turn against southbound US 101 vehicles.
|
|
Contractor/Consultant
Currently under WSDOT design.
|
|
Recent Progress
Project Management Plan received endorsement on February 13, 2007. Project Concept Approval was received on February 12, 2007. Project Definition was complete in April 2007. Hydraulics design is near completion.
|
|
Design Construction Impacts
Impacts will be evaluated upon further project definition.
|
|
Environmental Impacts / Compliance
Environmental impacts will be identified and evaluated during the preliminary engineering phase. Permits will be obtained and be in accordance with State and Federal regulations.
|
Impacts to Traffic
Construction of the new ramp will have minimal impacts to traffic.
|
| Project
Milestones |
Scheduled |
Attained |
Milestone Outlook |
|
Begin Preconstruction Engineering
|
May 15, 2005
|
Dec. 2005
|
Concept Approval on February 12, 2007. Project Management Plan endorsed on February 13, 2007.
|
|
Environmental Documentation Complete
|
May 5, 2008
|
|
The current design will have no direct impact to environmentally sensitive areas.
|
|
Right of Way Certification
|
November 5, 2008
|
|
The current design will fit within existing right-of-way.
|
|
Project Advertisement
|
October 6, 2008
|
|
Advertisement date can be advanced to February 2008.
|
|
Open to Traffic
|
September 31, 2009
|
|
Project completion date can be advanced to December 2008.
|