|
Project Title & Location
US 101/SR 3 On Ramp to US 101 Northbound - New Ramp.
|
Project Description
This project will construct a new northbound on-ramp from SR 3 to US 101 which will provide an efficient and safe roadway for motorist. The existing at grade intersection currently requires northbound US 101 traffic to make a left turn against southbound US 101 vehicles.
|
|
Contractor/Consultant
Currently under WSDOT design.
|
|
Recent Progress
The Hydraulics Report and Temporary Erosion and Sediment Control Plan have been completed and submitted for review & have been approved. The contract plans, estimate, and specifications have been submitted for agency review.
Project Development Approval was obtained on November 19, 2007.
|
|
Design Construction Impacts
Impacts will be evaluated upon further project definition.
|
|
Environmental Impacts / Compliance
The permits for the project are currently being obtained. Currently waiting on completion of the biological assessment.
|
Impacts to Traffic
Construction of the new ramp will have minimal impacts to traffic.
|
| Project
Milestones |
Scheduled |
Attained |
Milestone Outlook |
|
Begin Preconstruction Engineering
|
May, 2005
|
Dec. 15, 2005
|
Concept Approval on February 12, 2007. Project Management Plan endorsed on February 12, 2007.
|
|
Environmental Documentation Complete
|
Nov. 2007
|
|
The current design will not directly impact environmentally sinsitive areas.
|
|
Right of Way Certification
|
Oct. 2006
|
Nov. 14, 2007
|
The current design will fit within existing right-of-way.
|
|
Project Advertisement
|
Feb. 12, 2008
|
|
Advertisement has been advanced to February 2008.
|
|
Open to Traffic
|
Oct. 31, 2008
|
|
Project completion will be advanced to December 2008.
|