US 101 - Purdy Creek Bridge - Complete September 2009

Quarterly Project Report Update for Quarter Ending September 2008

Project Title & Location
US 101/Purdy Creek Bridge -Replace Bridge (Mason County)

Project Description
This project replaces the US 101 Purdy Creek Bridge in the Skokomish River Valley in Mason County. The Purdy Creek Bridge site is the lowest point of US 101. The hydraulics of the Lower Skokomish River frequently results in floods, closing US 101. This new bridge will accommodate the 100-year flood as well as possible changes to the course of the Skokomish River by constructing a raised roadway near Purdy Creek with a sufficient opening for flood water to pass through.

Contractor/Consultant
Quigg Bros., Inc.

Recent Progress
The project was awarded on 6/30/08 to Quigg Bros., Inc..   Construction began 7/21/08.    Recent progress includes placement of temporary erosion control measures and wall construction for the detour alignment. 

Design Construction Impacts
To date the project has been constructed as designed with only minor changes.  Additional utility relocates were required and have been completed.  The detour temporary wall type has been changed from geosynthetic to soldier pile.  Over-excavation at portions of the temporary wall locations was required. 

Environmental Impacts / Compliance
The project is being constructed in accordance with the project permits.  The project Best Management Practices are being maintained and are in good working order.

Impacts to Traffic
The new bridge will be adjacent to the existing. A detour roadway is being constructed that utilizes the existing bridge and a portion of the existing roadway to maintain  two lanes of traffic during construction. Two short duration lane reductions to one-lane one-way traffic under temporary signal system will be required.

Project Milestones Scheduled Attained Milestone Outlook
Project Definition Complete January 12, 2005 January 12, 2005 Complete.
Environmental Documentation Complete April 30, 2007 August 7, 2007 Complete.
Right of Way Certification August 10, 2007 February 20, 2008 Complete.
Contract Advertisement January 22, 2008 May 27, 2008 Complete.
Open to Traffic January 22, 2010 Project is on schedule.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $2.10 13.8%
Right-of-Way $0.63 4.1%
Construction $12.37 82.1%
Funded Project Costs $15.06 100%

Nickel funds included in above costs

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Neal Uhlmeyer, Project Engineer, (360) 412-3421.