US 101 - Purdy Creek Bridge - Complete September 2009

Quarterly Project Report Update for Quarter Ending June 2008

Project Title & Location
US 101/Purdy Creek Bridge -Replace Bridge ( Mason County)

Project Description
This project replaces the US 101 Purdy Creek Bridge in the Skokomish River Valley in Mason County. The Purdy Creek Bridge site is the lowest point of US 101. The hydraulics of the Lower Skokomish River frequently results in floods, closing US 101. This new bridge will accommodate the 100-year flood as well as possible changes to the course of the Skokomish River by constructing a raised roadway near Purdy Creek with a sufficient opening for flood water to pass through.

Contractor/Consultant
Berger/Abam

Recent Progress
Plans, Specifications, and Estimate are complete.  Contract has been advertised with bid opening scheduled for June 25, 2008.

Design Construction Impacts
 

Environmental Impacts / Compliance
This project design is governed by local flood ordinances and state and federal policy acts. 

Impacts to Traffic
The new bridge will be adjacent to the existing. A detour roadway will be constructed that utilizes the existing bridge and a portion of the existing roadway to maintain  two lanes of traffic during construction. Two short duration lane reductions to one-lane one-way traffic under temporary signal system will be required.

Project Milestones Scheduled Attained Milestone Outlook
Project Definition Complete January 12, 2005 January 12, 2005
Environmental Documentation Complete April 30, 2007 August 7, 2007 The USFW and NOAA concurrence on the BA is complete.  Environmental documentation is complete.
Right of Way Certification August 10, 2007 February 20, 2008 R/W Cert. 2 issued.
Contract Advertisement January 22, 2008 May 27, 2008
Open to Traffic January 22, 2010
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $2.10 13.8%
Right-of-Way $0.63 4.1%
Construction $12.37 82.1%
Funded Project Costs $15.06 100%

Nickel funds included in above costs

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Michele Britton, Project Engineer, (360) 570-6600