US 101 - Purdy Creek Bridge - Complete September 2009

Quarterly Project Report Update for Quarter Ending June 2007

Project Title & Location
US 101/Purdy Creek Bridge -Replace Bridge ( Mason County)

Project Description
This project replaces the US 101 Purdy Creek Bridge in the Skokomish River Valley in Mason County. The Purdy Creek Bridge site is the lowest point of US 101. The hydraulics of the Lower Skokomish River frequently results in floods, closing US 101. This new bridge will accommodate the 100-year flood as well as possible changes to the course of the Skokomish River by constructing a raised roadway near Purdy Creek with a sufficient opening for flood water to pass through.

Contractor/Consultant
Berger/Abam

Recent Progress
Geotech exploration is complete and lab testing is in progress. Plans, Specifications, and Estimates are under review and nearing 60% complete. Section 106 concurrence has been received from the Department of Archeology and Historic Preservation (DAHP. NOAA and USFW concur with the Biological Assessement. The project office continues to work closely with Mason County, Skokomish Tribe, WDFW, Ecology, and the Corps of Engineers to develop a permittable design. Relocation letters have been transmitted to Mason Co. PUD#1, Hood Canal Communications, and Qwest Communications. A meeting is tentatively scheduled for mid-June to coordinate utility project and relocation requirements. An offer on the diner parcel has been accepted and acquisition is nearing completion. Negotiation for the remaining parcels will begin in July 2007.

Design Construction Impacts
 

Environmental Impacts / Compliance
This project design is governed by local flood ordinances and state and federal policy acts.  The project design office is working with local state and federal governments in order to develop the best solution for the new bridge.

Impacts to Traffic
The replacement bridge will be built on a new alignment.  This will allow traffic to use the existing bridge during construction, eliminating the need for detours and other heavy traffic impacts.

Project Milestones Scheduled Attained Milestone Outlook
Project Definition Complete January 12, 2005 January 12, 2005
Environmental Documentation Complete April 30, 2007 The USFW and NOAA concurrence on the BA is complete.  SEPA/NEPA pending.
Right of Way Certification August 10, 2007
Contract Advertisement January 22, 2008
Open to Traffic January 22, 2010
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $1.0 7.7%
Right-of-Way $0.63 4.8%
Construction $11.39 87.5%
Funded Project Costs $13.02 100%

Nickel funds included in above costs

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Michele Britton, Project Engineer, (360) 570-6600