US 101 - Purdy Creek Bridge - Complete September 2009

Quarterly Project Report Update for Quarter Ending December 2007

Project Title & Location
US 101/Purdy Creek Bridge -Replace Bridge ( Mason County)

Project Description
This project replaces the US 101 Purdy Creek Bridge in the Skokomish River Valley in Mason County. The Purdy Creek Bridge site is the lowest point of US 101. The hydraulics of the Lower Skokomish River frequently results in floods, closing US 101. This new bridge will accommodate the 100-year flood as well as possible changes to the course of the Skokomish River by constructing a raised roadway near Purdy Creek with a sufficient opening for flood water to pass through.

Contractor/Consultant
Berger/Abam

Recent Progress
Plans, Specifications, and Estimate developed to 90% and reviewed. The project office continues to work closely with Mason County, Skokomish Tribe, WDFW, Ecology, and the Corps of Engineers. Environmental documentation complete. Permit applications have all been submitted. Corps of Engineers and DOE permits in hand. One Right of Way parcel complete and one in closing.  Negotiations continue on four of five remaining parcels. One parcel (WDFW) negotiating right of entry pending commission hearing to approve acquisition.

Design Construction Impacts
 

Environmental Impacts / Compliance
This project design is governed by local flood ordinances and state and federal policy acts. 

Impacts to Traffic
The replacement bridge will be built on a new alignment.  This will allow traffic to use the existing bridge during construction, eliminating the need for detours and other heavy traffic impacts.

Project Milestones Scheduled Attained Milestone Outlook
Project Definition Complete January 12, 2005 January 12, 2005
Environmental Documentation Complete April 30, 2007 August 7, 2007 The USFW and NOAA concurrence on the BA is complete.  Environmental documentation is complete.
Right of Way Certification August 10, 2007 R/W certification slipping but projected to be complete before advertisement. 
Contract Advertisement January 22, 2008 Contract advertisement date changed to March 3, 2008 to accommodate utility relocations and QA/QC review of plans.
Open to Traffic January 22, 2010
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $1.00 9.2%
Right-of-Way $0.63 4.8%
Construction $11.39 87.5%
Funded Project Costs $13.02 100%

Nickel funds included in above costs

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Michele Britton, Project Engineer, (360) 570-6600