US 101 - Mt. Walker NB & SB Passing/Truck Lane - Complete October 2007

Quarterly Project Report Update for Quarter Ending September 2006

Project Title & Location
US 101 - Mt. Walker NB & SB Passing/Truck Lane

Project Description
On the Olympic Peninsula there are limited areas for a traveler to pass slow-moving vehicles, creating a safety hazard and delaying motorist. This mobility improvement project provides passing opportunities on the US 101 corridor.

Contractor/Consultant
State forces are designing the project - it is not yet advertised or awarded.

Recent Progress
Right-of-way plans have been submitted and right-of-way acquisition can begin.

Design Construction Impacts

This project is currently under design. The hydraulic design and report needs some minor modifications. We are in the process of obtaining environmental permits and purchasing right of way.  

Environmental Impacts / Compliance

As designed, the project will have some adverse impacts to critical habitat. The impacts will have to be addressed and permits obtained prior to advertisement.

Impacts to Traffic

When construction begins, it is anticipated that some lane restrictions will occur. Single-lane, alternating traffic will be in place during the roadway widening and paving operation.

Project Milestones Scheduled Attained Milestone Outlook
egin Preconstruction Engineering ecember 15, 2005  December 15, 2005  
Right of Way Complete December 8, 2006
Environmental Document Complete December 8, 2006 This will not be attained. Currently anticipate completion by February 28, 2007.
Contract Advertisement January 8, 2007 Will not be attained due to delay in obtaining environmental compliance.  Current scheduled advertisement is March 26, 2007
Operationally Complete September 30, 2007 This should not be affected by the advertisement delay.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.40 17.2%
Right-of-Way $0.11 4.7%
Construction $1.82 78.1%
Funded Project Costs  $2.33 100.0%

Nickel funds included in above costs

2005 Transportation Partnership Account

$2.33 100.0%

  For more information, go to www.wsdot.wa.gov/projects

Jerry Moore, project manager, (360) 457-2575