US 101 - Mt. Walker NB & SB Passing/Truck Lane - Complete October 2007

Quarterly Project Report Update for Quarter Ending June 2007

Project Title & Location
US 101 - Mt. Walker NB & SB Passing/Truck Lane, located between Quilcene and Brinnon

Project Description
On the Olympic Peninsula there are limited areas for a traveler to pass slow-moving vehicles, creating a safety hazard and delaying motorist. This mobility improvement project provides passing opportunities on the US 101 corridor.

Contractor/Consultant
Lakeside Industries of Port Angeles, Washington

Recent Progress
The project has been awarded to Lakeside Industries on May 21.  Execution was June 5, 2007.  Construction has begun.

Design Construction Impacts
Blasting for some roadway excavation.  Cutting of some Olympic National Forest timber.  Impacting an existing Roadway Weather sensor.  All of these impacts have been addressed.

Environmental Impacts / Compliance
As designed, the project will have some adverse impacts to critical habitat. The impacts will be addressed by limiting some activities to certain hours of the day. All Permits have been obtained.

Impacts to Traffic
When construction begins, it is anticipated that some lane restrictions will occur. Single-lane, alternating traffic will be in place during the roadway widening and paving operation. Brief road closures will be required to accommodate possible rock blasting when the northbound lane is constructed.

Project Milestones Scheduled Attained Milestone Outlook
Begin Preliminary Engineering December 15, 2005  November 1, 2006 Completed.
Right of Way Certified March 1, 2007 May 25, 2007 Right of Way was completed and Forest Service lease concerns were addressed.
Environmental Document Complete November 15, 2006 April 2, 2007 All documentation is complete.
Contract Advertisement April 2, 2007 April 16, 2007 Construction has begun.
Operationally Complete October 30, 2007  
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.41 11.5%
Right-of-Way $0.11 3.1%
Construction $3.03 85.4%
Funded Project Costs  $3.55 100.0%

Nickel funds included in above costs

2005 Transportation Partnership Account

$3.55 100.0%

  For more information, go to www.wsdot.wa.gov/projects

Jerry Moore, project manager, (360) 457-2575