Skip Top Navigation

SR 99 - SR 525 Interchange Vic to Lincoln Way Vic – Paving & ADA Compliance - Complete November 2016

Project Status - Complete
A small map showing the intersection of SR 99 and SR 525 that will be paved.
View larger project map

A small picture showing some of the pavement that will be repaired
Aging pavement was repaired at SR 99 and SR 525.

A small picture of an area that needs a pedestrian ramp near SR 99 and SR 525
Pedestrian ramps were added for improved access in the project area.

Overview
WSDOT repaved nearly two miles of SR 99/Evergreen Way and SR 525, as well as a section of Lincoln Way between the two highways in the summer of 2016.

Approximately 17 pedestrian curb ramps were also improved or constructed to meet Americans with Disabilities Act standards.

How You Benefit
Cross GlyphImproves Safety
Repaving the highway surface eliminated cracks and wheel ruts in the pavement, making for a smoother, safer ride for drivers. New high-visibility striping was installed so drivers have an easier time seeing marked lanes, especially at night. Improvements to pedestrian curb ramps now provide a safer transition from roadway to sidewalk.
Dollar Sign Glyph Economic Incentive
This project reduces the need for emergency repairs, which are costly to taxpayers and can cause additional congestion during peak commute hours.

Partnerships & Cooperation
We coordinated this project with Snohomish County and the cities of Lynnwood and Everett.

Funding

Financial Data for PIN 109970N, 109970R, 152506B, 152506C
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $4,249
CWA $0
Total $4,249